(Solved):Question: D 1. For the given 6-M maintenance plan, the following activities will be done, links with Finish…

Question:

D 1. For the given 6-M maintenance plan, the following activities will be done, links with Finish to Start (F-S) with Zero duration Activity A B С E Predecessor A A A C&D Duration (Day) 8 5 6 8 20 1. Construct the project network (logic diagram)? 2. Identify the critical activities? 3. Identify the critical path? 4.